Brought down the temporary table so we have a place to eat. Kitchen is getting there 2 more weeks and we will be done with this room.
THINGS LEFT TO DO:
Cabinet baseboard trim
Cabinet top trim
Granite countertops
Install Cook top
Install Dish washer
Install drain and water to dish washer
Select Paint Colors
Paint Ceiling
Paint Walls
Install microwave
Hookup water to fridge
Replace 3 kitchen windows
Refinish kitchen door
Install outlets
Install Outlet covers
Crown Molding
Radiator Covers (qty 3)
Radiators painted (qty 3)
Closet Painted
Closet shelf installation
Closet Light installation
Paint & Install Closet Door
Cabinet frame for double oven
Oven installation
Cabinet trim kit for fridge
Paint cellar door
Replace Door knobs & locks (qty 3)
Install chandelier
Replace Storm Door
Trim molding to living room
Ceramic backsplash
Install Sink
Install faucet
Install water feed valves
Install braided water hoses
Install water valve for dish washer
Cabinet door alignment